SPECIAL REPORT; Coast infrastructure projects progressing well-KeNHA

187
0
[A section of the Dongo Kundu Bypass currently being constructed by a Japanese consortium, Fujita Corporation-Mitsubishi Corporation.The project is expected to decongest the ever-busy Likoni ferry channel which hampers development in the South coast region.Photo/Ahmed Omar/July, 23 2022].

Construction of multi-billion shilling infrastructure projects in Mombasa and Kwale counties is progressing steadily.

Kenya National Highways Authority (KeNHA) Director General (DG) Eng. Simon Omwono said all contractors awarded road and bridge construction in the Coastal region are on site working to meet scheduled completion dates of the projects.

He asked contractors to fast track ongoing construction works of all mega road, bridge and highway projects and complete them within the specified timeframe.

Eng. Omwono said among the mega projects are the Sh.22 billion Dongo Kundu Bypass Highway, also known as Mombasa Southern Bypass Highway and the Sh.4.5 billion Makupa Bridge.

The KeNHA senior official lauded the ongoing projects as a ‘game-changer’ noting that they would go a long way to solve some of the socio-economic problems faced by the people in the Coastal region.

He said the roads and bridges are being constructed to provide easy road connectivity to the people stressing that the focus on infrastructure projects will go a long way in improving infrastructure deficit in the region.

“Infrastructure is the bedrock of socio-economic development in any country and that is what these two particular mega ongoing projects exemplify,” he said.

The KeNHA DG expressed satisfaction with the quality of work done so far and said the government is committed to the completion of the entire projects in the Coastal region.

Contractors

Eng. Omwono said the Makupa Bridge contractor China Communications and Construction Co. Ltd (CCCC) and the contractor of phase two Dongo Kundu bypass a Japanese consortium, Fujita Corporation-Mitsubishi Corporation, are accelerating works on site as they seek to complete the projects.

The Dongo Kundu bypass is an important transport corridor for traffic destined to and from Tanzania and that to and from the interior of Kenya and beyond.

The bypass will decongest Mombasa Island and four bridges will be built in the swamps and across the open ocean water, as part of the highway.

Mega projects

He said the 8.96-km dual carriageway project involves construction of an interchange at the Likoni-Lunga Lunga highway and erection of two bridges one at Mwache – spanning 660 metres, and another at Mteza straddling 1,440 metres.

The KeNHA DG said the 457m long Makupa Bridge will replace the historic Makupa causeway that links Mombasa Island to the mainland.

The 120 meters Makupa causeway structure between Tudor and Port Reitz creeks was built in the 1920’s by the British colonial government and it has reportedly been interfering with the natural oceanic waves, the free flow of aqueous oxygen and it has also been a cause of damage to fish breeding grounds, besides causing pollution.

Eng. Omwono said the Makupa Bridge will help end delays and reduce accidents and will finally restore the status of Mombasa as a full Island city.

“Inland bound traffic of the Makupa Bridge is open but outbound traffic is yet to be opened because the approach roads are still ongoing,” he said and asked the contractor to complete the remaining works at a faster pace while maintaining quality in all the works.

The KeNHA boss spoke when he undertook a tour of the projects to inspect the progress accompanied by Coast Regional Commissioner (RC) John Elungata and Director of the Presidential Delivery Unit in the Coast region, Polycarp Onyango.

Impact

Dongo Kundu project resident engineer Moses Mwakira said the construction of the projects will make the region and the country a hub of transportation.

Eng. Mwakira said the Dongo Kundu Bypass project is 53% complete, to be operational in 2024 adding that the bypass will provide alternative routes to the South Coast, reducing Likoni ferry congestion.

Elungata while appreciating the scope of the projects said they will facilitate trade and movement to and from neighbouring Tanzania via Kwale hence fostering regional cooperation.

[KeNHA Director General Eng. Simon Omwono (pointing finger) accompanied by Coast RC John Elungata (centre) and Director of the Presidential Delivery Unit in the Coast region, Polycarp Onyango (donning red shirt) when he led the inspection of the ongoing construction projects in Mombasa and Kwale counties.Photo/Ahmed Omar/July, 23, 2022].

“The Special Economic Zone Development project at Dongo Kundu is one of the Vision 2030 flagship projects in the region,” he said.

A free trade zone, the Dongo Kundu Free Trade Zone, with 6,200 sites and ability to accommodate more than 10,000 business units is part of the planned development.